Elevator Update
We learned late today (Friday, Oct. 3) that the final elevator inspection by the government inspector AEDARSA is now scheduled for Thursday, October 9. This could mean that we enjoy …
The best of condo living in Calgary
We learned late today (Friday, Oct. 3) that the final elevator inspection by the government inspector AEDARSA is now scheduled for Thursday, October 9. This could mean that we enjoy …
The re-start of the elevator is still not scheduled. We have been delayed by faults discovered in the original wiring of the fire alarm system during testing. Our contractor has …
We have noticed that some KOP residents have been using hand-made parking passes for their visitors’ vehicles. This is a reminder that every KOP resident is allocated a laminated pass …
Today, on Wednesday Sept. 9, our electrical contractor is conducting a battery test on the new fire alarm control system that was installed as part of the elevator rebuild. For …
The new fire alarm system is now functioning. We no longer need fire watch patrols. Thanks to those who volunteered on this. The alarm system requires a formal inspection and …
The combination lock on the garbage room door is not functioning. Until this is fixed the door will not open. We have a locksmith scheduled to repair this lock this …
The fire alarm system is now disabled and will be so until the new fire alarm panel is installed and tested either Wednesday or Thursday next week (Sept. 3 or …
The elevator completion date has now shifted into September. It looks like the earliest we can plan for is September 15, and that date may still shift again. We are …
In the latest update re our elevator work, our contractors are estimating the elevator will be back in service at the end of August. The contractors are not able to …
The planned power outage at KOP was completed today by 10AM today. This outage did not affect all suites, so it is possible your unit did not have its power …